President Energy reports 50% output increase at Puesto Flores field
LONDON -- President Energy, the upstream oil and gas company with a diverse portfolio of production and exploration assets focused primarily in Argentina, provides an update in relation to its workover program at Puesto Flores field in Rio Negro Province, Argentina.
Key points
- Three previously producing wells at Puesto Flores field (President 90% - Ediphsa 10%) have now been successfully worked-over, repaired and put back in production
- Current Puesto Flores field production 2,100 bopd (June average to date over 1,800 bopd as wells come back on stream) with pressures stable
- This level of production represents an over 50% increase in the nine months since acquisition
- Work completed to date below budget
- Workover program extended from seven to eight wells with two of the eight wells to be worked over in Estancia Vieja field
Work on the first three wells of the current workover campaign has been completed under budget. Work is continuing on the next well in the series and, in light of the success achieved, the program has been enlarged by the addition of a further well.
The results of the workover program to date have been positive. Puesto Flores oil field production is presently running at approximately 2,100 bopd, with the average for June so far being over 1,800 bopd (as wells come back on stream), with pressures on the three worked over wells relatively stable.
This level represents an increase of over 50% in the nine months since the acquisition of the Concession. The success achieved so far is demonstrated by the fact that one of the wells has seen production increases which will achieve payback on the investment in under 30 days, significantly ahead of expectations. In addition, the efficient management of operations should permit the completion of an additional eighth well, taking the program to seven production well workovers and one water injection conversion, at the same budget as originally planned for seven wells.
Of the four producers remaining to be worked on after the current injector well is completed, two are now planned as oil well workovers at Estancia Vieja field.
In the meantime, preparatory work is continuing for start of the extended gas well tests at the Estancia Vieja field now scheduled to commence before the end of June.