Equinor's Aasta Hansteen Norwegian Sea goes online
STAVANGER -- Equinor and its partners started production from the Aasta Hansteen gas field in the Norwegian Sea. Gas from the Aasta Hansteen field is available to the market for the first time and together with the Polarled pipeline the field opens a new region for gas export to Europe.
“Aasta Hansteen is a pioneer! Located in 4,265 ft (1,300 m) of water, this is the deepest field development on the Norwegian continental shelf (NCS), the largest spar platform in the world, and a first on the NCS. The field now coming on stream is unique,” says Anders Opedal, Equinor’s executive V.P. for technology, projects and drilling.
Aasta Hansteen is located 186 mi (300 km) west of Sandnessjøen, far from other fields and in an area with harsh weather conditions. The field has been named after another pioneer: Feminist, social commentator, painter and author Aasta Hansteen.
The field development concept consists of a floating platform with a vertical cylindrical substructure moored to the seabed (spar platform). The platform is 1,112 ft tall (339 m) and weighs 70,000 tonnes. When the platform was towed to the field in April, it was the biggest tow on the NCS since Troll A in 1995.
The gas is produced from seven wells in three subsea templates. This is the deepest ever installation of subsea equipment on the NCS.
“Aasta Hansteen has been a complex and challenging development project, requiring us to take new technological steps together with our partners Wintershall, OMV and ConocoPhillips as well as the suppliers,” says Opedal.
Both Aasta Hansteen and the 299.5-mi pipeline (482-km) from the field to Nyhamna has the capacity to accommodate new discoveries. The first one, Snefrid North, is already under development, and will come on stream towards the end of 2019.
The recoverable resources at Aasta Hansteen, including Snefrid North, are estimated at 55.6 Bsm3 of gas and 353 MMboe (.6 MMsm3).
“The production from the Aasta Hansteen field will help secure long-term Norwegian gas export. With the infrastructure installed it will also be more attractive to explore around the platform and along the pipeline. This enables us to secure activity for many decades, in line with our ambitions for the NCS,” says Arne Sigve Nylund, Equinor’s executive V.P. for development and production Norway. The exploration activity in the area around the field has already increased, and several discoveries have been made.
Although the substructure and topside structure were built in South Korea Aasta Hansteen has generated big spin-offs for Norwegian supply industry. More than half of the topside equipment packages were produced in Norway, and the subsea equipment is also Norwegian. The subsea templates were built in Sandnessjøen and the suction anchors keeping the gigantic platform in place are produced in Mo i Rana. The platform was hooked up at Stord south of Bergen, which is also where much of the hook up and commissioning work was performed.
“In the operations phase the field will be operated from Harstad, base services will be delivered from Sandnessjøen and the helicopter traffic will go from Brønnøysund.
“In the project phase Aasta Hansteen and Polarled have generated spin-offs for slightly more than $1.8 billion (NOK 16 billion) in Norway, $150 million (NOK 1.3 billion) of which has benefited companies in Nordland and southern Troms, and there will be more in the years to come operating the field”, Nylund says.
Some 32 million man-hours have been put into the Aasta Hansteen project, which has cost about $4.3 billion (NOK 37.5 billion), which is a 2018 value. The $339 million (NOK 2.9 billion) increase since the submission of the plan for development and production (PDO) is due to the currency effect due to the weak NOK. This is within the uncertainty range assumed in the cost estimate for the PDO.