BW Energy begins production at Hibiscus oil field offshore Gabon
(WO) – BW Energy announced that production has safely started from second well of the Hibiscus / Ruche Phase 1 development in the Dussafu license offshore Gabon. Production performance from the well has been in line with expectations and is currently stabilized at approximately 6,000 bpd.
The DHIBM-4H well was drilled as a horizontal well from the BW MaBoMo production facility to a total depth of 4,800 meters into Gamba sandstone reservoirs on the Hibiscus field. Following completion, the Borr Norve jackup has commenced drilling operations on the third production well (DHIBM-5H).
The drilling campaign targets four Hibiscus Gamba and two Ruche Gamba wells, which are expected to add approximately 30,000 bpd of total oil production when all wells are completed in early 2024. The oil produced at Hibiscus / Ruche is transported by pipeline to the BW Adolo FPSO for processing and storage before offloading to export tankers.
Separately, the commissioning and testing of the second gas lift compressor is ongoing on the BW Adolo. The compressor, which will support production from the six Tortue wells, is expected to commence its final commissioning phase in the next few weeks and, once fully operational, will add another 3,000 bpd.