BW Energy starts drilling at new production well offshore Gabon
(WO) — BW Energy announced the start of drilling of the first production well on the Hibiscus / Ruche Phase 1 development in the Dussafu Block offshore Gabon. Drilling operations commenced on schedule in the first week of January and in line with the target of producing first oil in March 2023.
The Borr Norve jackup arrived on location in late December and immediately started preparations for the drilling campaign. The first production well, DHIBM-3H, targets the Gamba sandstone reservoir on the Hibiscus field and is expected to take just over two months to drill and complete.
Installation of flexible pipelines and risers, completing the 20-kilometer connection between the BW MaBoMo production facility and the FPSO BW Adolo, was also finalized last week.
The initial Hibiscus / Ruche Phase 1 drilling campaign targets the Hibiscus and Ruche fields which are expected to add approximately 30,000 bpd of total oil production when all wells are completed in early 2024.
As previously guided, the new gas lift compressor to support production for the six existing Tortue wells was lifted onboard the BW Adolo in December. Installation work is ongoing.
Commissioning and start-up of the compressor is expected to commence immediately after first oil from Hibiscus / Ruche which has priority during the current high-activity period onboard the FPSO.